The City of Isle of Palms has scheduled a ribbon cutting for 10 a.m. today, Thursday, November 19, at the corner of Waterway Boulevard and Forest Trail. It marks the official opening of the rebuilt multi-use path and the completion of Phase 2 of the Waterway Blvd Flood Barrier Project, according to the City's announcement.
Most people will know it as the place they walk the dog, run before work or ride to the marina. The project was designed around a different idea. The path between 21st and 41st Avenue is now part of the island's drainage system, and it is built to stop two things from moving through that system. Tide is kept from pushing in from the Intracoastal Waterway, and runoff, including what dogs leave behind, is kept from flowing out into it. The engineering covers the first job. Daily use of the path decides how well the second one works.
A sidewalk you can measure in feet of elevation
The path came out of the December 2023 nor'easter. The City says it caused heavy tidal flooding along the marsh side of the island, where homes and public infrastructure near Waterway Boulevard were hit by water coming off the Intracoastal. What began as a path repair became a flood project.
Hillary Aton, project manager with the Mount Pleasant engineering firm Thomas & Hutton, explained the before-and-after numbers to Island Vibes in July:
| Before | After Phase 2 | |
|---|---|---|
| Path elevation | Below 5 feet in places, as low as 4.27 feet | Raised to 7 feet |
| Width | Old asphalt path | About 8 feet in most areas |
| Outfall pipes to the Intracoastal | No backflow protection described | In-line check valves on all outfall pipes |
| Length of this phase | About 1.68 miles, 21st to 41st Avenue |
Those low points under 5 feet mattered. Aton told the magazine that "overtopping has occurred repeatedly during extreme tide events" on the old path. At 7 feet, the path is meant to work as a continuous tidal barrier together with the berms built earlier. Phases 1 and 1a, finished in fall 2025, raised holes 9 and 10 of the Harbor Golf Course at Wild Dunes, the holes that run alongside the Intracoastal. The City calls that earlier work "largely invisible" because it blends into the golf course grass.
The walking surface needed the work regardless. In Live 5's July coverage, Waterway residents said roots and broken asphalt had made the old route hazardous for walking and biking. Construction stayed out of most people's way. In April, with crews working between 21st and 30th Avenue, the City kept the route open on temporary compacted gravel while paving went on. An August update reported several weeks of delay from utility conflicts. On October 12 the City announced Phase 2 was complete.
The valves under your feet
The raised path is the part you see. The more important part is underground. Phase 2 added localized drainage that carries stormwater beneath the path and installed check valves on every outfall pipe that drains into the Intracoastal. Aton told Island Vibes the valves "are designed to prevent tidal backflow into the drainage system, reduce 'sunny day' flooding and preserve system capacity during storm events."
Sunny-day flooding happens when a high tide comes up through the storm drains with no rain at all. A check valve lets water leave the pipe and keeps the tide from coming back in. That makes the outfalls a key part of the project. They are where the street drains into the marsh, and the path now sits over them.
Paying for the work took the project well past its first estimate. Phase 2 funding was approved in August 2024 at about $1.08 million, with a federal share of $979,931.70 and $108,881.30 left for the City or another source, Island Vibes reported. By July 2026, Live 5 reported that the broader project, first budgeted at just over $1.1 million, had grown to about $7 million. City leaders were also weighing a $151,337 change order for utility lines.
Why there's a dog station every two blocks
The outfalls that let rainwater out also carry whatever the rain picks up on the way, and the City's Environmental Advisory Committee has been testing what that is.
Its January 2026 meeting packet describes two rounds of sampling:
- Fall 2024 baseline. Eight island outfalls were sampled after rain for coliform bacteria, nitrogen, phosphorus, oil and grease, pH, suspended solids and PFAS. The Waterway Boulevard outfall at 36th Avenue near Forest Trail ranked among the three highest-concern residential sites because of high nitrogen, phosphorus and suspended solids. The Waterway outfall at 30th Avenue ranked lowest of the baseline sites.
- 2025 targeted screening. Dry-weather, low-tide samples were taken at 25th Avenue, 36th/Forest Trail and Myrtle Avenue. DNA analysis of the 25th and 36th Avenue samples found dog fecal bacteria. A later rain-event sample at 25th Avenue showed no human E. coli.
The 36th Avenue outfall near Forest Trail ranked among the highest-concern sites, and today's ribbon cutting is at Waterway Boulevard and Forest Trail.
With the path done, Public Works installed ten Doody Calls dog-waste stations along Waterway Boulevard, starting at 21st Avenue and repeating every two blocks to 41st Avenue. An eleventh station sits on the Breach Inlet beach path, and all of them are serviced every Monday, according to the City's notice. The EAC plans follow-up water testing at the Waterway outfalls in one to two years to see whether contamination drops. The check valves keep the tide out of the drains. Whether the next test finds cleaner water at those outfalls depends on how people use the stations along the path.
Walking it from 21st to 41st
The project now shapes the route itself. Here is what you pass from one end to the other:
- 21st Avenue. The south end of Phase 2 and the first Doody Calls station. The next one is two blocks up, and the spacing holds all the way north.
- The 25th Avenue outfall. One of the two sites where the 2025 DNA testing found dog bacteria.
- 29th Avenue. A short detour leads to Bark Park, behind the Isle of Palms Recreation Center. The City's facilities page lists weekday gym hours as generally 8 a.m. to 4 p.m., with the Rec Center closed Sundays.
- Forest Trail and the 36th Avenue outfall. Site of today's ceremony and of the baseline's highest-concern Waterway outfall.
- 3607–3615 Waterway Boulevard and Fire Station No. 2. These are the two remaining gaps in the flood barrier, covered under the next section.
- 41st Avenue and the marina. The north end. The Isle of Palms Marina at 50 41st Avenue advertises a ship's store, a deli, boat rentals, and kayak and paddleboard rentals.
In winter, the path also connects to the beach. Under the City's dog rules, dogs may be off leash on the beach from 4 p.m. to 10 a.m. between September 15 and March 31. Owners must carry a leash, keep the dog under voice command and clean up after it. If your loop ends at Breach Inlet, the eleventh Doody Calls station is on that beach path.
The next high tide, and the last two gaps
The tidal side of the project gets its next scheduled test soon. SCDES's South Carolina King Tides initiative, posted on MyCoast, lists November 24–27 as the next predicted king tide window, based on NOAA predictions for the Charleston Harbor tide station. The state uses the program to document how extreme tides affect beaches, waterways and public infrastructure, and it accepts photo reports from the public. When Aton spoke with Island Vibes in July, she said "the tidal protection components have not yet been tested by a major coastal storm or severe tidal event," and added that early drainage improvements were already showing benefits. A morning walk during that window will show how the path and the outfalls handle a high tide. If you take photos from the public path, MyCoast accepts them.
The barrier also isn't continuous yet. Phase 3 is meant to close the two gaps near 3607–3615 Waterway Boulevard and Fire Station No. 2. The City is weighing options that include raising a section of golf cart path or building a retaining wall behind the five homes that remain in the gap. It says more details will come as engineering and design move forward. Until then, the 1.68 miles you walk today are finished, and the last few hundred feet of the barrier are still being designed.
For more on the island, see our Isle of Palms neighborhood page and our summer guide to living around the beach renourishment sand pipes.
At Lowcountry Luxury Properties, we follow City projects like Waterway Boulevard closely because they shape daily life on the island. If you'd like to talk through what this path and the Phase 3 plans mean for your part of the marsh side, schedule a personalized consultation and we'll walk through it with you.