James Island Road Projects Fall 2026: Folly Road and Beyond

James Island will see several road projects this fall, and most of the differences between them come down to paperwork. On August 27, 2026, Charleston County Council approved the construction contract for Phase 1 of Rethink Folly Road. A few months earlier, the Town of James Island voted not to sign the municipal agreement for a separate South Carolina Department of Transportation safety project on the same road, so the state cut the town's segments from it. Over on Fort Johnson Road, a project funded by the county sales tax is moving ahead on its own schedule.

The result is a corridor where the improvements follow jurisdiction lines. Three different programs pay for the work, and each one covers different stretches.

Two Folly Road projects

Two separate efforts carry nearly the same name, and the news this year has blurred them together.

Rethink Folly Road is the community plan adopted in 2016. It covers the corridor from the Wappoo Cut Bridge to Folly Beach and is run by a steering committee that includes the Town of James Island, the City of Charleston, Charleston County, the City of Folly Beach and others. Its Phase 1 is the project that just won its contract.

The SCDOT safety audit grew out of a May 2023 Road Safety Audit of Folly Road from Old Folly Road to Old Folly Beach Road. Charleston Moves, a bike and pedestrian advocacy group on the steering committee, describes it as "a separate but related process." The state needed a signed municipal agreement from each local government before it could move to full design. That agreement is where the split happened.

The audit's baseline explains why the state wanted it. From January 2018 through December 2022, that section of Folly Road recorded 2,103 vehicle crashes, 15 pedestrian crashes and 21 bicycle crashes. 525 caused injuries and 6 were fatal.

Phase 1, the stretch that finally has a contract

Phase 1 runs from about Ellis Creek to Wilton Street, just past Walmart. The steering committee picked this segment in November 2017 because it had the highest collision rates on the corridor. The plan calls for a widened sidewalk, wider bike lanes with green paint at conflict points, and improved intersections. The longer design history also includes three improved intersection crossings and better transit stops.

Phase 1 has been in the works since 2017. The design was paid for with a mix of 2016 Half-Cent Sales Tax dollars, federal funds, the Town of James Island and the City of Charleston, and Charleston Moves says the project went through "repeated failed bid attempts" before it was ready to build. So the town is a funding partner in Rethink Folly Phase 1 even though it declined the SCDOT agreement. One program does not depend on the other.

The research has not turned up a public contractor name, contract amount or start date for Phase 1. A July Citizen Portal report said a contractor had been chosen but did not name it. Until a schedule comes out, "approved" is the most accurate word for this stretch.

What the town opt-out removed

According to Live 5's July 9 report, the town opted out after residents and businesses raised concerns about the proposed raised medians. SCDOT had already scaled those medians back. At a March 24, 2026 City of Charleston committee meeting, the department presented concepts that kept raised medians mainly where side-angle crash rates are highest. The City approved its agreement and the town did not.

The state cut two town segments, roughly Camp Road to Patterson Avenue and a long stretch from around Bur Clare Drive to Fort Johnson Road. At the July steering committee meeting, SCDOT listed what came out of the project as a result:

Removed item Where it would have applied
Resurfacing The entire roadway
Access control High-crash areas
CARTA bus stop improvements Along the corridor
Northbound sidewalk Just past Charleston County EMS Station 4 to Grimball Road
Sidewalk, driveway and crosswalk work Grimball Road and Fort Johnson Road intersection, in front of SC Federal Credit Union and the Exxon
Leading pedestrian interval Grimball and Fort Johnson intersection, a signal timing change that gives people on foot a head start

Improvements are still planned on the parts of the road owned by the City of Charleston and Charleston County. Southbound on Folly Road, that means safety work will appear on some blocks and skip others. The pattern matches municipal boundaries, not the crash map.

Two things still reach every segment. SCDOT has jurisdiction over Folly Road and has committed to quarterly maintenance, including street sweeping, drain and gutter cleaning, bike lane cleaning and vegetation trimming. The Folly Road Corridor Overlay also requires redevelopment projects to install a 12-foot multiuse path along their frontage. Charleston Moves says many parcels already have path pieces that "will someday link together." Under the overlay, the path grows one redevelopment at a time, whichever jurisdiction the parcel sits in.

Fort Johnson Road runs on a different funding source

A mile or so east, a different set of rules applies. The Fort Johnson Road intersection projects are paid for by the 2016 Transportation Sales Tax referendum and managed by Charleston County. They did not need the SCDOT agreement, so they kept moving while the Folly Road project was being cut back.

Fort Johnson at Camp Road is now a "traversable urban compact roundabout," the county's term for a design built to handle mixed traffic. It opened to vehicles on Monday, August 10, and the sidewalks stayed closed with a pedestrian detour in place at opening. In its September 24 release, the county said the roundabout, drainage improvements and utility relocations were finished and signage was being installed.

Fort Johnson at Secessionville Road is next. The intersection is getting a traffic signal with crosswalks, pedestrian refuge areas, pedestrian signals and dedicated turn lanes. The curb and gutter are poured, utility relocation is done, and signal installation is scheduled to begin this month. Construction on the pair of intersections is expected to continue until June 2027. The county holds quarterly public updates at James Island Town Hall, 1122 Dills Bluff Road, and the most recent one was September 29. No public account of that meeting had been published as of this writing.

Some of the crosswalk and sidewalk work that came out of the Grimball and Fort Johnson intersection on Folly Road is the same kind of work going into Fort Johnson's other intersections under the county program. The difference is the funding source, not the type of work.

Maybank and Woodland Shores is finished

On the north end of the island, the county completed the Maybank Highway and Woodland Shores Complete Streets work in summer 2026. It added a mid-block crossing on Maybank with flashing beacons and a refuge island, a raised landscaped median with fencing, and 500 feet of new sidewalk along Maybank. The project started in March 2025, and the county had projected a June 2026 finish.

This project includes a raised median, the same feature that led the town to opt out on Folly Road. It went in on Maybank because the county ran this project directly.

Central Park Road and Riley Road

The next project to affect daily driving belongs to the City of Charleston. Live 5 reported on September 21 that the City was preparing to approve a $4.5 million contract for the final phase of the Central Park Drainage Basin project. The basin covers about 500 acres, running from James Island Creek near Central Park Road north toward Maybank Highway, and from the Woodland Shores and Riverland areas east toward Folly Road. It would be the first major project on the basin's eastern side. Matthew Fountain, the City's director of stormwater management, called it "the last piece of that original project framework" in a basin that has seen "somewhere between $10 million and $20 million" in total investment.

Live 5 reported that temporary closures were expected on Riley Road, Central Park Road and the EME Apartments driveway, with work possibly starting within about a month of final approval and finishing by the end of 2027. The City's bid document for the project adds a detail. Traffic access along Riley Road must be maintained for the full length of construction, because the road has no alternate access route for residents or emergency services. Final approval, the contractor's name and a dated closure schedule had not been confirmed in what we found. Treat this one as pending.

The fall map, by stretch

Corridor Who runs it Status as of early October 2026
Folly Road, Ellis Creek to Wilton Street Rethink Folly Phase 1, county contract Contract approved August 27; start date not announced
Folly Road, town segments SCDOT safety project Removed after the town declined its agreement
Folly Road, City and county segments SCDOT safety project Improvements still planned
Fort Johnson at Camp Road County, 2016 sales tax Roundabout open since August 10; signage going in
Fort Johnson at Secessionville County, 2016 sales tax Signal installation scheduled to begin in October; project runs to June 2027
Maybank Highway at Woodland Shores County Completed summer 2026
Central Park drainage, Riley and Central Park roads City of Charleston $4.5 million contract pending; Riley Road access required throughout

For more on how the island's corridors and businesses fit together, see our James Island neighborhood guide and our look at one Camp Road address and its restaurant turnover.

If you'd like help understanding how a particular project, like the Phase 1 work or the Central Park drainage closures, affects your own street or a property you're watching, Lowcountry Luxury Properties is glad to walk through it with you. Schedule a personalized consultation and we'll go over the public records together.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.